I-100Four kinds of interior · eight stages · 18 weeks, typically
Interiors, drawn to the millimetre.
We design and build the insides of homes, offices, cafés and shops the way we draw buildings: every room detailed to the millimetre, built by craftspeople from nearby, in materials from within two hundred kilometres.
I-100 · Plan of a flat · living, dining and kitchen · 1:50 · in millimetres
1Reclaimed teakShelving wall · pol houses in the walled city, 4 km
2KhadiSofa covers · woven in Dholka, 48 km
3CaneTwo armchairs · woven in the walled city; the cane is from Assam
4TerrazzoFloor, cast on site · chip from Ambaji, 180 km
5Shell-lime plasterWalls, three coats · Khambhat lime, 92 km
6BrassPendants and pulls · Kansara Pol, 5 km
7Dhrangadhra sandstoneCounters · Dhrangadhra, 108 km
I-110Three details
What we decide before the carpenter arrives.
1I-110Detail 1, sheet I-110: Drawer front at the kitchen counter · 1:5
Drawn to the millimetre.
Every cupboard, shelf and counter is drawn at 1:5 before a sheet is cut: the timber, the hinge, the runner, and the 3 mm gap between two drawer fronts. A detail that has to be worked out on site with a tape has already gone wrong.
2I-110Detail 2, sheet I-110: Section at a south window · the noon sun
Daylight first, then light fittings.
We draw where the noon sun falls in May and in December before placing a single light point. Then each fitting is drawn to its task — 2700 K over the table, 3000 K at the counter — on a switch you can find in the dark.
3I-110Detail 3, sheet I-110: The palette below, by distance · 0–200 km
Nothing from further than 200 km.
The teak, stone, brass and cloth come from within a day's drive of the studio, and so do the people who work them. The one exception is cane, and the drawing says so.
What an interior commission covers.
Layouts
Furniture plans at 1:50 for every room, measured from the room as it was built, not from the brochure.
Joinery
Kitchens, wardrobes, beds and shelving, drawn at 1:5 and made by carpenters we have worked with since 2016.
Lighting and electrical
A ceiling plan with every light point, switch and socket, checked against where the furniture will actually stand.
Materials and finishes
Stone, timber, plaster and cloth chosen from samples you take home, each with its source and its price.
Furniture
Pieces made to order in teak, cane and Sankheda lacquer, or found, restored and placed.
Renovation
Walls moved, bathrooms rebuilt and wiring replaced, including in homes where people are still living.
Two ways to work with us.
The drawings are the same either way. What changes is who builds from them, and who answers for it.
Two ways to work with us.
DesignDrawings, specifications and site visits. Your contractor builds.
Design and buildTurnkey: our crews and vendors, one contract, one schedule.
Drawings
The full set: plans at 1:50, elevations at 1:20, joinery at 1:5
The same set
Who builds
Your contractor, from our drawings
Our carpenters, masons, electricians and painters
On site
A visit every week, and a written note after each
Our supervisor every working day, and the same weekly visit
Contracts
Two: one with us, one with your contractor
One, with us
Schedule
Your contractor's, checked by us every week
One schedule, and keeping it is our job
Bills
Your contractor bills you directly
Every bill shared at cost, plus our stated management fee
Carpentry warranty
Your contractor's
Five years, in writing
Suits
Clients with a contractor they already trust
Clients who want one name answerable for all of it
Design
Drawings, specifications and site visits. Your contractor builds.
Drawings
The full set: plans at 1:50, elevations at 1:20, joinery at 1:5
Who builds
Your contractor, from our drawings
On site
A visit every week, and a written note after each
Contracts
Two: one with us, one with your contractor
Schedule
Your contractor's, checked by us every week
Bills
Your contractor bills you directly
Carpentry warranty
Your contractor's
Suits
Clients with a contractor they already trust
Design and build
Turnkey: our crews and vendors, one contract, one schedule.
Drawings
The same set
Who builds
Our carpenters, masons, electricians and painters
On site
Our supervisor every working day, and the same weekly visit
Contracts
One, with us
Schedule
One schedule, and keeping it is our job
Bills
Every bill shared at cost, plus our stated management fee
Carpentry warranty
Five years, in writing
Suits
Clients who want one name answerable for all of it
I-120Plans at index scale · drawn from a typical area
Four kinds of interior.
Homes
Flats and bungalows, new or lived in, across Lucknow.
Carpet area
600–3,000 sq ft
Typical time
12–20 weeks
Workplaces
Offices and studios for ten to sixty people, planned around how the work moves through the room.
Carpet area
1,000–8,000 sq ft
Typical time
10–16 weeks
Cafés and restaurants
Rooms to eat and wait in, with the kitchen drawn alongside the cook who will work in it.
Carpet area
500–4,000 sq ft
Typical time
8–14 weeks
Shops
Small shops where the goods are handled before they are bought: cloth, books, brass, food.
Carpet area
300–2,000 sq ft
Typical time
6–10 weeks
I-130Schedule of stages · 18 weeks, typically
From the first tape measure to the last hinge.
StageWhat you receive
123456789101112131415161718
Billed
1
Measurement and brief
Every room measured and drawn at 1:50, the existing wiring and plumbing surveyed, and your brief written down in your words.
10%billed
Weeks 1–2
Weeks 1–2
2
Design and 3D views
Furniture layouts, every wall drawn as an elevation, and 3D views of each room from where you will stand in it. Two rounds of changes.
15%billed
Weeks 3–6
Weeks 3–6
3
Material selection
A sample box to take home: each stone, veneer, handle and cloth, with its source and its price.
5%billed
Weeks 6–7
Weeks 6–7
4
Civil work and false ceiling
Walls moved, waterproofing ponded for 48 hours before tiling, floors laid, and the ceiling framed with every light point marked before it is boarded.
15%billed
Weeks 8–11
Weeks 8–11
5
Carpentry and furniture
One drawer built full size for you to open, then the kitchen, wardrobes and shelving, made in the workshop and fitted on site.
25%billed
Weeks 10–15
Weeks 10–15
6
Electrical and lighting
Wiring on its own circuits, every switch where the furniture plan puts it, and each fitting hung and aimed.
10%billed
Weeks 9–15
Weeks 9–15
7
Painting and finishes
Plaster or paint in three coats, stone polished, and every hinge, runner and handle adjusted.
12%billed
Weeks 15–17
Weeks 15–17
8
Styling and handover
Furniture placed, curtains hung, a deep clean, the as-built drawings, and the warranty in writing.
8%billed
Week 18
Week 18
110%
215%
35%
415%
525%
610%
712%
88%
Share of the contract, stage by stage
Weeks are typical for a three-bedroom flat of about 1,500 sq ft built by our crews. Each stage is invoiced when it is finished, at its share of the contract, so you never pay ahead of the work.
I-140Materials legend
Eight materials, and how far each one travels.
Drawn as a legend: each swatch carries the hatch our drawings use for it. Distances are from the studio, on the same 0–350 km scale as every project sheet; past our 200 km line, a material is redlined.
1
Reclaimed teak
Pol houses being rebuilt in the walled city
4 km
2
Brass
Cast and turned in Kansara Pol
5 km
3
Hand-moulded brick
Kilns at Sanand
32 km
4
Khadi
Handspun and woven in Dholka
48 km
5
Shell-lime plaster
Lime burnt at Khambhat, slaked on site
92 km
6
Dhrangadhra sandstone
Quarries at Dhrangadhra
108 km
7
Terrazzo
Cast on site, with marble chip from Ambaji
180 km
8
Cane
Woven in the walled city; the cane comes from Assam
2,100 km
Drawn to one scale, 0–350 km. The red tick is our 200 km line; anything past it is redlined, and its bar runs off the end.
I-150Four interiors · plans at one scale
Selected interiors.
1I-150Plan · 135 m² · to the sheet's one scale
Teak Flat
Satellite, Ahmedabad
Type
Home
Carpet area
1,450 sq ft
Time
18 weeks
Scope
Design and build
A three-bedroom flat in a 1994 block, rebuilt around one wall of reclaimed teak that holds the books, the television and the puja. The family stayed in two rooms for the first nine weeks.
Reclaimed teak
Terrazzo
Shell-lime plaster
Khadi
2I-150Plan · 204 m² · to the sheet's one scale
Print Room
Navrangpura, Ahmedabad
Type
Workplace
Carpet area
2,200 sq ft
Time
14 weeks
Scope
Design
An office for a block-printing company, with a sample library in shallow drawers and a table long enough to unroll six metres of cloth. Built by the client's own contractor from our drawings.
Dhrangadhra sandstone
Reclaimed teak
Brass
3I-150Plan · 84 m² · to the sheet's one scale
Kitli
Law Garden, Ahmedabad
Type
Hospitality
Carpet area
900 sq ft
Time
10 weeks
Scope
Design and build
A tea room with a terrazzo counter cast in place. The cane chairs are re-woven every second monsoon rather than replaced, by the weaver who made them.
Terrazzo
Cane
Brass
Shell-lime plaster
4I-150Plan · 59 m² · to the sheet's one scale
Loom Works Shop
Alkapuri, Vadodara
Type
Retail
Carpet area
640 sq ft
Time
8 weeks
Scope
Design and build
The Bhujodi weavers' first shop outside Kachchh. Shawls are kept flat in shallow teak drawers, so that customers open them, not the staff.
Reclaimed teak
Khadi
Shell-lime plaster
Plans are drawn from each interior's type and carpet area, all at one scale: they show the programme and the size, not the layout as built.
Fees, explained.
Two figures are agreed in writing before any work starts, and neither moves unless the brief does.
Design fee
A rate per square foot of carpet area, fixed in the agreement before we measure. Changes asked for after the drawings are approved are priced before they are drawn.
Execution
On design and build, materials and labour at cost, with every bill and invoice shared, plus a management fee stated as a percentage in the contract.
Payments
Tied to the eight stages above. Each is invoiced when its stage is finished, at its share of the contract.
Site visits
Weekly visits are part of the design fee for as long as the schedule runs; past it, each visit is billed at a fixed rate.
Questions we are asked.
How long does an interior take?
About eighteen weeks for a three-bedroom flat, from the first measurement to handover; eight to ten for a small shop. The schedule above is the one we draw for a typical flat, and yours is drawn by the end of week 3.
Can we keep our existing furniture?
Yes, and we usually suggest it. Pieces you want to keep are measured in the first week and drawn into the plans; those worth restoring go to our carpenters and come back with the rest of the work.
Can we live at home while the work is done?
Often, when the work can go room by room. We close off the rooms being worked on, keep a bathroom running, and agree the noisy hours with you. A new kitchen or full rewiring usually means two to four weeks away.
Is there a warranty on the carpentry?
Five years on the carpentry and hardware we make and fit, in writing from handover: hinges, runners, shutters and joints. We come back after the first monsoon to adjust anything that has moved.
How often will you be on site?
Every week, on the same day, with a written note afterwards, whichever way you work with us. On design and build, our supervisor is also on site every working day.
Can our own contractor do the work?
Yes; that is the Design commission. We draw the full set, answer your contractor's questions and check the work every week. We do not price or manage their bills.
What if we change our minds half-way?
A change is redlined on the drawings, priced and dated, and you sign it off before anyone starts on it. Nothing is changed on site on the strength of a phone call.
Tell us about the rooms.
A floor plan or a sketch, a few photographs, the date you need to be in by, and the budget you can actually spend. We reply within five working days, and quickly if the work is not for us.